Change the timescale of your project’s timeband

Tips on how to change the timescale of your project’s timeband in Office Timeline add-in

Lucen Timeline
·
May 28, 2013
·
2
min read
In this article

Last updated on March 11, 2024

Your project might span multiple years or just a few days. In all cases, you can adjust the time intervals on the project’s timeband to be displayed in the format you need: Days, Weeks, Months, Quarters, or Years.

Here is how you can do it easily and quickly in just four steps:

1. Open your timeline slide in PowerPoint and select your graphic’s timeband.

Timeband scale in months

2. With the timeband selected, go to the Timescale settings section in the Office Timeline Style Pane on the right side.

Select Timescale settings

3. From the Scales tab, pick a timescale from the options available (Hours/Minutes, Days, Weeks, Weeks (ISO), Quarters or Years). The add-in will automatically update your timeline, repositioning the tasks and milestones.

Change timeband scale

In the example below, we have switched the timescale from months to weeks.

Timescale in weeks

4. While in the Scales tab, if you use the most advanced edition of Office Timeline, you’ll also have the option to display multiple time scales featuring different time units. In our example below, we have opted for Months, Weeks, Days:

Multiple timescales option

Tip: In the Settings tab, you will also find the Language control for the timeband. Use it to change the language of your timeband’s scale if you have an international audience.

Change timeline language option

Find more resources on timescales in the Office Timeline Add-in Support Center:

Are you running the latest version? Check our updates page and download the latest build to make sure it runs smoothly.